The company has concluded a contract for execution of design works on tying-in of a cracking furnace of world-famous company Technip of capacity 36 tones per hour by ethylene in the scope of expansion of Ethylene Plant Shop.
Placement of equipment at the site specified by the Customer, laying of all process utilities, integration of the new furnace in the existing ethylene production process as well as to the enterprise automated control system will be performed in the course of the project implementation. A full range of works on designing including obtaining of positive conclusion of the State Expert Review is planned to be completed in July 2014.
Kazanorgsintez OJSC that is one of the leaders in the industry is the project customer.